How to use this calculator
- Check your local building code or deck plans for the footing size and depth. This tool does not size footings.
- Enter the number of footings.
- Choose a round tube form and its diameter, or a square pad and its side length.
- Enter the depth below grade and how far the footing will stand above grade.
- For tubes, pick the tube length you'll buy so the calculator can count how many you need.
- Optionally, add prices to see the total cost. Results update as you type.
Tube volumes use the size on the label. Some tubes are slightly smaller inside, for example a 12 in tube measuring 11.5 in, so the 10% extra covers small differences.
Worked example
6 footings in 10 in tube forms, 42 in below grade and 2 in above, with 10% extra and 4 ft tubes:
- Height of each footing: 42 + 2 = 44 in
- Concrete per footing: π × 5² × 44 = 3,456 in³ ÷ 1,728 = 2.0 ft³
- Total: 2.0 × 6 × 1.10 = 13.2 ft³ (0.49 yd³)
- Bags, rounded up: 13.2 ÷ 0.60 = 22.0 → 22 × 80 lb; ÷ 0.45 = 29.3 → 30 × 60 lb; ÷ 0.375 = 35.2 → 36 × 50 lb fast-setting; ÷ 0.30 = 44.0 → 44 × 40 lb
- Tubes: each footing needs 44 in of tube, so one fits in each 4 ft tube: 6 tubes (22 ft in total)
Frequently asked questions
How many bags of concrete fill a 10 inch or 12 inch tube?
A full 4 ft length of 10 inch tube holds about 2.2 cubic feet, which is about 3.6 bags of 80 lb mix or 4.8 bags of 60 lb mix. A 4 ft length of 12 inch tube holds about 3.1 cubic feet, which is about 5.2 bags of 80 lb mix or 7 bags of 60 lb mix. Per foot of depth, that is roughly 0.9 bags (10 inch) and 1.3 bags (12 inch) of 80 lb mix. Always round up.
How deep do deck footings need to be?
Deck footings must sit on undisturbed soil below your local frost line, so frost heave cannot lift the deck. Codes based on the International Residential Code generally require at least 12 inches below grade, and the frost line can be 36 to 48 inches or more in cold climates. Your local building department sets the required depth and size.
Should I use a round tube form or a square pad?
Tube forms make neat round piers, are quick to set up and use less concrete for a given depth. A wider square pad, or a tube on top of a wider base, spreads the load over more soil, which helps on soft ground or for heavy decks. The right choice depends on your deck design, soil and local code.
How high above grade should a deck footing be?
Finish the top of the footing a couple of inches above the ground so water drains away and wood posts are not in contact with soil. Use a metal post base on top. Quikrete says its QUIK-TUBE forms can be used up to 3 ft above grade.
Should I use bagged concrete or order ready-mix for footings?
For a handful of footings, bags are usually easiest because you can mix them at each hole. Once you need more than about a cubic yard, around 45 bags of 80 lb mix, ready-mix delivery can save a lot of work, but many suppliers charge a short-load fee for small orders, and the truck needs to reach your holes.